Masdar has marked the completion of the Lockhart Solar and Storage complex in California, a 950 million dollar project built by Terra-Gen, the American developer it owns jointly with Igneo Infrastructure Partners.
The complex carries 365 megawatts of solar generation and 173.7 megawatts of battery storage, a combined 538.7 megawatts. It sits on roughly four thousand acres of private land in San Bernardino County and connects to the grid at Southern California Edison's Kramer Junction substation. A ribbon cutting was held at the Hinkley facility and the announcement was made on the thirteenth of November.
The 950 million dollar figure is Masdar's own and is published without qualification, so it is not stated whether it describes investment, total project cost or capital expenditure. Offtake is covered by agreements with corporate buyers and by long term power purchase agreements with California load serving entities, none of which has been named.
The ceremony marks the completion of the whole complex rather than the day it began generating. The final phase, Lockhart Solar PV IV at 80 megawatts, reached commercial operations in July, and financial close on the third and fourth phases was reached in December of last year. More than 925,000 solar modules and 248 battery enclosures are installed on the site, which took over 880,000 construction hours across four years and supported more than a thousand jobs on site.
The structure of the deal says more about Gulf energy capital than the megawatts do. Masdar is not the builder or the direct owner here; it holds the developer alongside an infrastructure fund manager, and the operating company carries the development risk. That is a deliberate shape for a sovereign backed investor entering a market where permitting, interconnection queues and tax equity structuring are specialist local businesses rather than things a foreign developer can learn on the job.
It also explains the pace. Masdar says it has put around three billion dollars into the United States so far and plans a further twenty billion over the next decade, against a target of up to 25 gigawatts by the end of the decade. Reaching that from a standing start would be implausible; reaching it by buying a platform with an existing pipeline and an existing interconnection position is a different proposition, and Lockhart is the first large asset to come through that route at scale.
Khaleefa Almheiri, the president and chief executive of Masdar Americas, said the completion of Lockhart demonstrated the scale of the company's ambitions in the United States. The project is expected to generate more than forty million dollars in property tax revenue over its operating life.