Representatives of Scan Granitt and Betonmast Buskerud-Vestfold hold the signed collaboration agreement in the Scan Granitt stone showroom.

Betonmast Buskerud-Vestfold has signed a collaborative contract to develop a new production facility for Scan Granitt, a Norwegian fabricator of stone surfaces. The contractor announced the agreement on 12 November 2026.

The planned building covers roughly 5,000 square metres. The builder described the construction cost as an estimate of 60 million kroner excluding value added tax rather than a fixed contract sum, which is the normal position at this stage of a collaborative appointment. A first phase is planned to run to Christmas, construction start is planned for March 2027, and the build period is put at eleven months.

The collaborative model, known in Norway as samspill, is the point of the award rather than a detail of it. Under it the contractor is brought in before the design is fixed and works alongside the client and the consultants to settle the solution, with the price firmed up as the design matures. For a specialist manufacturer that is building once, the attraction is access to buildability and cost advice at the stage when changes are still cheap. The trade is that the client carries more of the early cost uncertainty, which is precisely why the stone firm's figure is published as an estimate.

The underlying driver is production capacity. Stone fabrication is equipment-led and space-hungry: saws, waterjet cutters and polishing lines need both floor area and the slab handling and dust extraction to serve them, and a facility laid out around current equipment is hard to expand incrementally. Replacing rather than extending is often the cheaper answer, and it allows the layout to be designed around material flow from slab intake to finished surface.

For the builder, the contract sits alongside two Oslo-region conversion awards announced by sister companies in the same month, and it is a different kind of work: a purpose-built industrial facility for a single owner-occupier rather than the adaptation of standing commercial stock. A construction start planned for March 2027 and an eleven month programme put completion in the first part of 2028.