The United States Nuclear Regulatory Commission has issued a construction permit for the Long Mott Generating Station in Calhoun County, Texas, the first such authorisation granted to a high-temperature gas-cooled reactor in nearly 60 years.
The permit, announced on 9 November 2026, covers a plant of four Xe-100 reactors designed by X-energy. The regulator says the station will mainly produce high-temperature industrial steam for a chemicals site at Seadrift on the Texas Gulf coast operated by Dow Inc., with surplus electricity sent to the grid. It is the third advanced reactor construction permit the commission has issued this year.
The decision carries several firsts for the agency. It is the first approval of a multimodule advanced reactor facility, the first of a pebble-bed core design and the first authorisation of online refuelling, and it is the first reactor of its type reviewed under the Licensing Modernization Project framework. Staff completed the safety evaluation in October, a month ahead of schedule, after an environmental assessment and a finding of no significant impact were issued in the spring.
"We delivered on the 18-month schedule," said chairman Ho K. Nieh, who added that the commission can conduct rigorous safety reviews on predictable timelines.
The permit authorises construction only. Long Mott Energy, the applicant, must still obtain a separate operating licence before it may load fuel or operate the reactors, and no date has been set for that review.
The commercial shape of the project is unusual, and the published ratings explain why. The regulator's own project record puts the station at 320 megawatts electric and 800 megawatts thermal across the four modules, with each module rated at roughly 80 megawatts electric, or about 200 megawatts thermal if its output is taken as steam rather than as power. That either or is the point. The plant is being built primarily as a heat supplier to an industrial customer, and electricity is the residual rather than the product. Industrial process heat has been among the hardest parts of heavy industry to decarbonise, because it needs temperatures that wind and solar generation cannot deliver directly, and a reactor sited at the customer's fence line is one of the few answers that does not depend on a hydrogen supply chain that does not yet exist at scale.
Regulatory risk, however, is only one of the risks this project carries. The United States Department of Energy has cost shared the reactor programme through its Advanced Reactor Demonstration Program, and it describes the plant as covering the site's industrial steam needs for 60 years, but a construction permit is not a final investment decision. The permit settles whether the design can be licensed and leaves the questions of cost, schedule and board approval exactly where they were. For a first of a kind build those are usually the binding constraints, and the recent record on large nuclear construction in the country gives boards reason to wait for firmer numbers before committing capital.